Project Details

Griffith Company
LA Metro Doran Street Grade Separation Segment 1 Glendale
Project Information
Project owner
LA Metro Doran Street Grade Separation Segment 1 Glendale
Bid due date
05/05/2026, 07:00 PM
Request for information due date
05/01/2026
Description
LADWP Advanced Utility Relocation
1. Installation of LADWP underground conduit, new power poles, and electrical vault in Doran Street and W. San Fernando Road.
B. Doran Street Grade Separation Segment 1 City of Glendale.
1. Removal of existing improvements, except in the area immediately adjacent to the rails, which will be completed by SCRRA contractor(s).
2. Construction of roadway including curb, curb and gutter, sidewalk, driveways, and miscellaneous improvements within the sidewalk and driveways.
3. Construction of asphalt pavement on crushed miscellaneous base materials.
4. Installation of storm drain and catch basins.
5. Protection and/or relocation of existing utilities in place and/or coordination with the utility owners, as indicated on the Plans.
6. Removal of asphalt pavement within the at-grade railroad concrete panel vehicle crossing in coordination with SCRRA contractor(s) as indicated on the Plans.
7. SCRRA's contractor(s) will be constructing the removal of rail, ties, crossing panels and railroad signaling equipment, including conduits, wiring, and active warning devices. Contractor shall coordinate their Work with SCRRA's contractor(s) work to avoid delays affecting performance, the project schedule and to avoid interference with each other's work as follows:
a. Contractor shall complete all roadway and traffic signal improvements located outside of the existing roadway footprint prior to requesting the long-term
Required Certificates
SB
DVBE
Location & Contacts
Location
Doran St and San Fernando Road, Glendale, CA 91205
Contact name
Deanne Roehl
droehl@griffithcompany.net
Phone
7148829098